construction · webcor
Meyking places.
A building this size is a tribe of tribes: owners, designers, dozens of trade partners and thousands of craftspeople, all meyking the same thing, in the same place, in the right order.
At Webcor I worked on how that work flows — lean construction, and the planning systems that keep the trades pointed the same way. On most of these projects I was a small part of a very big team.
Harvey Milk Terminal 1
San Francisco International Airport · Austin-Webcor JV
The part I’m proudest of wasn’t a wall or a gate. It was the planning system we built to coordinate the work — Last Planner sessions in the big room, an old hangar on the airfield; a six-week look-ahead on the wall; huddles on the apron with the airport still running around us — and how well it held under the weight of a project that size.
also
-
Salesforce Transit Center
Transbay · San Francisco
A light touch here — I was Webcor’s senior manager of performance excellence while it came together.
-
Moscone Center expansion
San Francisco · 2018
Another small part of a big one: steel going up, March 2018.
-
UC Merced
Merced, California
Tower cranes over the Central Valley, as the campus grew.
-
Four Seasons
Los Angeles
Rebar and formwork, the deck taking shape below the hills.